The complete 22-hour window
This was not only a PR #80 incident. From PR #76 opening at 20:30 JST on July 30 to PR #80 merging at 17:58 the next day, GitHub records 21 hours and 29 minutes. Pre-PR implementation and post-merge production work extend the user-visible duration beyond 22 hours.
Nine PRs (#76, #77, #78, #79, #80, #82, #84, #85, and #86) contained 90 commits, 265 changed-file entries, and 25,930 changed lines. They triggered 88 Actions runs, including 27 failures and 14 cancellations, with about 476.6 minutes of cumulative workflow elapsed time.
There was no durable checkpoint for 8 hours and 18 minutes between 22:03 and 06:21. Four other PRs were also handled while PR #80 remained active.
PR #80 breakdown
PR #80 itself took 11 hours and 37 minutes from creation to merge on July 31, 2026.
| Metric | Measured value |
|---|---|
| Commits | 77 |
| Changed files | 87 |
| Additions / deletions | 14,964 / 455 |
| Review submissions | 78 |
| Codex reviews | 23 |
| Review threads | 57 (28 P1, 29 P2) |
| GitHub Actions runs | 49 |
| Successful / failed / cancelled | 22 / 13 / 14 |
| Runner time | about 216.4 minutes |
The 13 failures comprised six visual-capture failures, five shared /data test-state failures, and two shared SQLite or mutable fake-response failures. The final Codex review on head d7ca1b5c4809 arrived 22 seconds after merge and opened two P2 threads. The process did not verify review completion on the exact current head.
Root causes
- Nine PRs ran as one open-ended effort without a fixed stop condition.
- An 8-hour, 18-minute implementation block had no durable checkpoint.
- CI/CD, Pages, previews, Space deployment, secrets, runner isolation, and UI were combined in PR #80.
- Four other PRs caused context switching while PR #80 was active.
- Trust boundaries and state transitions were discovered serially in review.
- Reviews were requested after micro-commits instead of stable feedback waves.
- Slow visual capture was mixed into deterministic CI.
- Tests shared
/data, SQLite files, and mutable fakes. - No gate combined exact-head review, unresolved threads, checks, and scope.
A terminal Codeberg Container Registry HTTP 503 added delay, but the official Forgejo mirror resolved it and it was not the primary cause.
Preventive workflow
The default scope budget is 25 files, 2,000 changed lines, and 20 commits. Split work that exceeds any limit. Use an explicit exception only for work that cannot be safely separated.
Create a validated coherent checkpoint within 45 minutes of starting implementation. If that is unsafe, record the blocker and next decision point instead of continuing silently. Diagnose after the same failure occurs twice. Keep one active implementation PR per workstream unless repositories, branches, acceptance criteria, and merge order are demonstrably independent.
One worktree per issue
Start file-changing issues in a dedicated branch and worktree:
git fetch origin
git worktree add ..\OpenFace-issue-123 -b fix/issue-123 origin/mainReserve the main worktree for synchronizing main, integration tests, and post-merge deployment. Keep each issue worktree limited to one issue, one set of acceptance criteria, and one PR. Do not implement issues concurrently when they modify the same files or state schema; merge the prerequisite PR first, then update the dependent worktree from main. Move newly discovered unrelated work into another issue and worktree.
After merge and production verification, confirm there are no unpushed commits or user-owned changes before removing the worktree and local branch.
CI owns builds, lint, unit and integration tests, configuration checks, and documentation builds. Tests use isolated temporary directories. Visual QA stays outside CI: capture the real Compose or production runtime and have a person open the images.
Before merge, run:
python scripts/check_pr_merge_readiness.py `
--repo Sunwood-ai-labs/OpenFace `
--pr 87The guard blocks drafts, stale or missing Codex reviews, unresolved threads, pending or failed checks, and unexplained scope-budget violations. Review requests, reactions, and approvals on older commits never authorize merge. Use gh pr merge --match-head-commit <verified-sha> so the merge itself cannot silently accept a newer head.